Sundance 310P Substation Upgrades
Location: Wabamun, Alberta
Date of Completion: 2017
Customer: AltaLink Management LP
Voltage: 240kV
Scope: Brownfield EPC
Located west of Edmonton, Alberta, the Sundance power plant is the largest coal-fired electrical generating facility in western Canada.
Rising Edge was responsible for upgrades, including replacing 15 existing air blast 240kV breakers with ABB HPL-300B1 live tank breakers.