Clover Bar Substation Bay Addition

Location of Project  Edmonton, Alberta, Canada Project Complete Year  May 2024 Project Scope To support Air Products’ proposed new net-zero hydrogen production facility, local utility is needed to construct a…
Location of Project  Edmonton, Alberta, Canada
Project Complete Year  May 2024
Project Scope To support Air Products’ proposed new net-zero hydrogen production facility, local utility is needed to construct a new 240kV single circuit, above ground transmission line from the existing Clover Bar substation to a proposed new substation which will be owned and operated by Air Products. Project includes constructing approximately 4.5km of above-ground 240kV transmission line from the Clover Bar substation to the proposed customer-owned substation within the Air Products’ site located in the Clover Bar area, and adding two (2) new 240kV circuit breakers, associated switches and equipment within the existing Clover Bar substation fence line. 
Rising Edge’s Scope of Work

Rising Edge was responsible for the procurement and construction of Clover Bar E987 Substation Bay expansion by adding two (2) 240kV circuit breakers and all other associated equipment within the substation fence. 

This included but was not limited to: installation of screw piles, caps, gussets and all required welding and weld inspection work, installation of new structures, in-ground ground grid addition, all apparatus equipment grounding and bonding, new yard CT/PT Junction Boxes, installation of new major apparatus equipment (two (2) 240kV circuit breakers, two (2) sets of 240kV CVTs, three (3) sets of 240kV CTs, four (4) of 240kV disconnects switches (Manual), and one (1) 240kV disconnect switches (MOD)), and all other supporting work.

Voltage 240kV
Service / Tags
  • Brownfield 
  • Substation 
  • Construction
  • Utilities 

Related Posts

No results found.