Location of Project  Lethbridge, Alberta, Canada Project Complete Year  November 2024 Project Scope Local utility required an upgrade to an existing substation with two (2) separate scopes where transformer replacement…
Location of Project  Lethbridge, Alberta, Canada
Project Complete Year  November 2024
Project Scope

Local utility required an upgrade to an existing substation with two (2) separate scopes where transformer replacement would be required and the protection upgrade of an incoming line. 

Rising Edge’s Scope of Work

Rising Edge was responsible for executing two (2) scopes:

I. Engineering, procurement, construction, commissioning of complete T1 transformer replacement – this included salvaging existing PT and foundation, inspection of new transformer and installation of the new 138kV Transformer and its foundation, along with dressing and oil filling

II. Engineering, procurement, fabrication, testing, and commissioning of transformer protection upgrades – salvaging two existing P&C modules, installation of two new P&C modules, rewiring all CT/VT, DSP, I/O, and communication modules

Voltage 138kV 