| Location of Project | Kipling, Saskatchewan, Canada |
| Project Complete Year | June 2024 |
| Project Scope |
A 200MW wind facility, consisting of 36 wind turbines and underground medium-voltage collector system. It matches the province’s other largest wind generation facility. |
| Rising Edge’s Scope of Work |
Rising Edge was responsible for the engineering, procurement, construction of the Bekevar-Yotin 230/34.5kV substation as well as installation of the corresponding collection network system – installation, termination, and commissioning of 34.5kV power cables, continuous ground, and fiber optic. |
| Voltage | 230kV |
| Service / Tags |
|
Kipling Wind Substation and Collector
Location of Project Kipling, Saskatchewan, Canada Project Complete Year June 2024 Project Scope A 200MW wind facility, consisting of 36 wind turbines and underground medium-voltage collector system. It matches the…