Location of Project | Bowmanton, Alberta, Canada |
Project Complete Year | November 2024 |
Project Scope |
This project is the complete substation upgrades and installation of new electrical equipment to the utility’s substation. The utility wanted to address the need to mitigate voltage concerns on the 240kV double circuit transmission lines in the southern region of the province. |
Rising Edge’s Scope of Work |
Rising Edge was responsible for modifying the Bowmanton substation to add three (3) 240kV 100MVA shunt capacity banks, add three (3) 240kV breakers, and add or modify any associated equipment as required. |
Voltage | 240kV |
Service / Tags |
|
244s Bowmanton Voltage Support