Location of Project  Fort Saskatchewan, Alberta, Canada Project Complete Year  Under Execution (Est. 2027) Client Name Dow Chemical Project Scope Dow’s Path2Zero project is a major industrial decarbonization initiative intended…
Location of Project  Fort Saskatchewan, Alberta, Canada
Project Complete Year  Under Execution (Est. 2027)
Client Name Dow Chemical
Project Scope Dow’s Path2Zero project is a major industrial decarbonization initiative intended to modernize and expand the Fort Saskatchewan complex through new hydrogen, utilities, and process infrastructure that will enable substantially lower-carbon manufacturing operations.
Rising Edge’s Scope of Work Installation, assembly, energization, test & commission, and support of the project’s high-voltage electrical infrastructure, including transformers, GIS equipment, substations, and associated power system components for the UPI Path2Zero facility. 
Voltage 300 / 138 / 25 / 15kV 
Service / Tags
  • Industrial
  • Substation
  • GIS Installation
  • Commissioning
  • Construction
  • Canada