| Location of Project | Hilda, Alberta, Canada |
| Project Complete Year | 2022 |
| Client | Renewable Energy Systems (RES) |
| Project Scope | Hilda Wind Power project is in Cypress County, Alberta and was developed as a 100MW wind facility comprising 20 turbines, underground medium-voltage electrical cabling, substation, and access roads, with a 138kV transmission connect to the Alberta electrical grid. |
| Rising Edge’s Scope of Work | Engineering, procurement, construction (EPC) of 138/34.5kV substation supporting the interconnection of the facility |
| Transmission Facility Operator | AltaLink Management LP |
| System Operator | Alberta Electric System Operator (AESO) |
| Voltage | 138/34.5kV |
| Service / Tags |
|
Hilda Wind Farm Substation
Location of Project Hilda, Alberta, Canada Project Complete Year 2022 Client Renewable Energy Systems (RES) Project Scope Hilda Wind Power project is in Cypress County, Alberta and was developed as a 100MW wind…