Wheatland Substation and Collector

Location of Project  Near Drumheller, Alberta, Canada Client Potentia Renewables Project Complete Year  2022 Project Scope Wheatland Wind Farm project is located approximately 30km southeast of Drumheller. It is a 120MW operating wind facility with…
Location of Project  Near Drumheller, Alberta, Canada
Client Potentia Renewables
Project Complete Year  2022
Project Scope Wheatland Wind Farm project is located approximately 30km southeast of Drumheller. It is a 120MW operating wind facility with 24 utility-scale wind turbines and associated turbine infrastructure that includes an underground electrical collection system, access roads, and construction of a new wind collector system. Turbines are connected through a combination of 34.5kV above ground and underground collector lines connecting to the newly constructed Badlands substation. 
Rising Edge’s Scope of Work Engineering, procurement, construction (EPC) of 144/34.5kV collector substation and 40km of underground 34.5kV collector line system connecting the wind generation facility. 
Transmission Facility Operator ATCO Electric Ltd.
System Operator Alberta Electric System Operator (AESO)
Voltage 144/34.5kV 
Service / Tags
  • Renewable Energy
  • EPC
  • Substation
  • Collector System
  • Control Building Fabrication
  • Canada